42-Desk Tech Office Relocation, Reading
A 42-desk SaaS company relocation delivered over one weekend with zero Monday downtime — including secure server transport and full desk crate-hire.
How the move ran
- T-8 weeksMove project kickoff
Named coordinator assigned. Weekly stand-ups with the client's operations lead.
- T-4 weeksCrate hire distributed
Colour-coded crates delivered to every desk with pre-printed labels and a packing brief for staff.
- T-1 weekIT freeze planned
IT partner coordinated. Server rack decommissioning slot booked for Friday 6pm.
- Fri 18:00Decommission
Server room shut down and packed into anti-static crates. Desks broken down.
- Sat all dayTransport & reassembly
Two vans running in rotation. New office desks assembled and wired for power by end of Saturday.
- Sun 14:00IT re-commission
Server rack live. Every desk tested with the client's IT team.
- Mon 08:30Business as usual
42 people arrived to a working office, working phones and coffee in the kitchen.
Challenges & how we solved them
Outcome
- 42 staff back to work on time Monday
- No IT downtime, no lost hardware
- Delivered under budget vs original spec
"The Dimond team ran this like a proper project, not a removal. Weekly calls, a coordinator we could actually reach, and Monday morning was a non-event. Exactly what we hoped for."